The aim of the executive project is to ensure that electrical as well as IT and networking installations are conducted following a standard based on the readiness assessment that will be applied in every health facility.
RESULTS
CS ROMÃO
- ELECTRICAL WORK PLAN
- Installation of improved Earthing System;
- Installation of Neutral Earthing System and Distribution Board in Main Switch/Server Room;
- Installation of new connectivity to the satellite offices;
- Installation of external wall plugs to supply continues power during power outage;
- Installation of battery banks to supply 1500kw for 4 hours during power outages;
- Repairs to all fault wall power sockets
- IT NETWORK & INFRASTRUCTURE
- Installation of 19” 27U self standing rack cabinet;
- Installation of LAN: around 14 network ports;
- 8 workstations with UPSs;
- Laser printer;
- Barcode printer and scanners;
REFERENCE DOCUMENTS
CS ROMÃO
- Projecto-Executivo-da-Unidade-Sanitária-do-Romão-SESP
- Romão Health Facility Maps
- Anexo-01_Centro-de-Saude-Romao_Projecto-Electrico_Planta
- Anexo-02_Centro-de-Saude-Romao_Projecto-Electrico_-Estrutura-de-Alimentacao-Geral
- Anexo-03_Centro-de-Saude-Roamao_-Esquema-Unifilar-do-Quadro-Electrico-Poc
- Anexo-04_Projeccao-Modular-do-Quadro-PoC
- Anexo-05_Legenda-do-quadro-Back-Up-nao-Back-Up
- Anexo-06_Centro-de-Saude-Romao_-Projecto-Informatico_-Planta.
- Anexo-07_Planta-da-LAN
- Anexo-08_Legenda-do-Servidor-_Portas-de-Entradas-Saidas